Weekly Report: 04/13/13

Project Progress

  • Contractor, CPDC, constructed PCC sidewalk and brick alleys on the south side of the 1300 block.

  • Subcontractor, F & F Landscaping prepared planting beds along the corridor.

  • Subcontractor, Omni Excavators, constructed granite curb and gutter on the north and south sides of the 1300 block.

  • Subcontractor, MC Dean, removed traffic signals L82 and L89 at the intersection of U Street NW and 11th Street NW; and removed cables.

Public Outreach/Coordination

  • Informed the public about roadway resurfacing that is set to take place beginning May 6th.

  • Spoke businesses about continuing work in their block and answered questions regarding activities.

  • Helped pedestrians enter and exit business on the corridor as the contractors worked to excavate and construct sidewalks.

Weekly Report: 03/08/13 (click to expand)

Click here to view this week's report in pdf format

Project Progress

  • Contractor, CPDC, constructed PCC sidewalk on the south side on the 1100 and on the north side of the 1200 block.

  • Contractor, CPDC, installed curb and gutter at the SW corner of 11th Street NW and U Street NW; and at the SE corner of 12th Street NW and U Street NW; and on the south side of the 1200 block of U Street NW.

  • Subcontractor, Omni Excavators, constructed curb and gutter on the north side on the 1200 and 1300 blocks.

  • Subcontractor, MC Dean, installed streetlight foundation on the south side of the 1000 block and electrical conduit between manholes M34 and M33; and D36 and D38.

Public Outreach/Coordination

  • Spoke with 1200 block businesses about continuing work in their block and answered questions regarding activities.

  • Helped pedestrians enter and exit business on the corridor as the contractors worked to excavate and construct sidewalks.

Weekly Report: 02/22/13 (click to expand)

Click here to view this week's report in pdf format

  • Contractor, CPDC, installed brick sidewalk, brick driveway aprons and PCC sidewalk on the south side on the 1000 block of U Street NW.

  • Contractor, CPDC, excavated for the curb and gutter, and sidewalk.

  • Subcontractor, Omni Excavators, constructed curb and gutter on the south side on the 1000 and 1100 blocks on the south side.

  • Contractor, CPDC, installed inlet #26 and inlet #28.

  • Subcontractor, MC Dean, installed electrical conduit between manholes M31 and M34.

Public Outreach/Coordination

  • Continued to speak with 1100 block businesses about continuing work in their block and answered questions regarding activities.

  • Helped pedestrians enter and exit business on the corridor as the contractors worked to excavate and construct sidewalks.

Weekly Report: 02/15/13 (click to expand)

Click here to view this week's report in pdf format

Project Progress

  • Contractor, CPDC, installed brick sidewalk, PCC sidewalk on the south side on the 1000 block of U Street NW, brick driveway aprons, handicap ramps and bus pads on the south side on the 1100 and 1300 blocks.

  • Subcontractor, Omni Excavators, constructed curb and gutter on the south side on the 1000 block and at the bus pad on the SW corner of 11th Street NW.

  • Contractor, CPDC, installed inlet #26 and inlet #35.

Public Outreach/Coordination

  • Continued to speak with 1100 block businesses about continuing work in their block and answered questions regarding activities.

 

Weekly Report: 02/08/13 (click to expand)

Click here to view this week's report in pdf format

Project Progress

  • Contractor, CPDC, excavated and installed curb and gutter, brick sidewalk, and PCC sidewalk on the north side on the 1000 and 1100 blocks of U Street NW.

  • Contractor, CPDC, performed electrical work at the intersection of 12th Street NW.

Public Outreach/Coordination

  • Contractor, CPDC, performed electrical work at the intersection of 12th Street NW.

  • Attended monthly ANC1B meeting and informed them of construction activities and plans to move forward with construction in additional blocks.

 

Weekly Report: 02/01/13 (click to expand)

Click here to view this week's report in pdf format

Project Progress

  • Contractor, CPDC, excavated and installed curb and gutter, brick sidewalk, and PCC sidewalk on the north side on the 900 and 100 blocks of U Street NW.

  • Contractor, CPDC, installed basin on 10th Street NW going west.

  • No work was completed on two days due to weather conditions.

Public Outreach/Coordination

  • Spoke with 1000 block and 1100 block businesses about scheduling/timeline and answered questions regarding activities.

  • Ensured that pedestrian access to sidewalk and business on the 1000 block was maintained as CPDC constructed concrete driveway.

 

Weekly Report: 01/23/13 (click to expand)

Click here to view this week's report in pdf format

Project Progress

  • No work took this week due to weather conditions.

Public Outreach/Coordination

  • Spoke with 1000 block occupants about scheduling/timeline and answered questions regarding activities.

  • Spoke with ANC commissioner in regards to grant money allocations for the 1300 block of U Street.

  • Responded to concern regarding temporary ramp conditions. The issue was corrected immediately and followed-up with DDOT.

  • Ensured that pedestrian access to sidewalk and business on the 1000 block was maintained as CPDC constructed concrete driveway.

Weekly Report: 01/18/13 (click to expand)

Click here to view this week's report in pdf format

Project Progress

  • Subcontractor, Omni Excavator, excavated and installed curb and gutter, brick sidewalk, and PCC sidewalk on the north side on the 900 block of U Street NW.

  • Contractor, CPDC, excavated and installed concrete driveway on the north side U Street NW on the 1000 block.

  • Contractor, CPDC, installed basin on 10th Street NW going west.

Public Outreach/Coordination

  • Spoke with 1000 block occupants about scheduling/timeline and answered questions regarding activities.

  • Spoke with ANC commissioner in regards to grant money allocations for the 1300 block of U Street.

  • Responded to concern regarding temporary ramp conditions. The issue was corrected immediately and followed-up with DDOT.

Weekly Report: 01/11/13 (click to expand)

Click here to view this week's report in pdf format

Project Progress

  • Contractor, CPDC, excavated and installed curb and gutter on the north side at the intersection of Vermont Avenue NW and U Street NW.

  • Contractor, CPDC, excavated and installed curb and gutter, brick sidewalk, and PCC sidewalk on the north side on the 900 block of U Street NW.

Public Outreach/Coordination

  • Contractor, CPDC, excavated and installed curb and gutter, brick sidewalk, and PCC sidewalk on the north side on the 900 block of U Street NW.

  • Held 1000 block field meeting with occupants of the 1000 block and distributed information about upcoming construction activities and schedule.

Weekly Report: 12/14/12 (click to expand)

Click here to view this week's report in pdf format

Project Progress

  • Contractor, CPDC, installed brick sidewalk and installed PCC sidewalk on the 900 block on the north side.

  • Contractor, CPDC, excavated and subcontractor, Omni Excavators, installed curb and gutter on the median at the intersection U Street NW at Vermont Avenue NW.

  • Contractor, CPDC, placed traffic signal poles on temporary bases on the 1200 and 1300 blocks of U Street NW.

  • Contractor, CPDC, excavated the trench for the conduit and backfilled it after conduit was encased in concrete.

  • Subcontractor, M.C. Dean, laid electrical conduit on the 1100 and 1200 blocks of U Street NW on the south side; and performed electrical trench repair.

Public Outreach/Coordination

  • Addressed concerns about maintaining entry into U Street businesses with CPDC. They will continue to make certain access is maintained at all times.

 

Weekly Report: 12/07/12 (click to expand)

Click here to view this week's report in pdf format

Project Progress

  • Contractor, CPDC, installed brick sidewalk and brick driveway apron on the 900 block on the north side.

  • Contractor, CPDC, installed double bus pad in front of the U Street Metro Station on the 1200 block of U Street NW.

  • Subcontractor, M.C. Dean, laid electrical conduit on the1100 and 1300 blocks of U Street NW on the south side.

Public Outreach/Coordination

  • Addressed a noise concern created by excavation equipment on the 900 block of U Street NW after being reported by a business whose office is located on said block.

  • Attended monthly ANC 1B meeting. No questions or concerns were raised.

  • Spoke with Lincoln Theatre staff about upcoming events in order to coordinate future construction activities.

Weekly Report: 11/30/12 (click to expand)

Click here to view this week's report in pdf format

Project Progress

  • Contractor, CPDC, excavated and installed curb and gutter between 9th Street NW and 10th Street NW on the north side.

  • DDOT inspector performed density testing along the roadway under concrete repair before placing concrete.

  • Contractor, CPDC, constructed bus pads on the 1300 block of U Street NW.

  • Subcontractor, M.C. Dean, laid electrical conduit on the 1200 and 1300 blocks of U Street NW on the south side; and at the intersection of 13th Street NW on the north side.

Public Outreach/Coordination

  • Addressed the noise created by steel plates on the 1200 block of U Street NW after being reported by a DC employee whose office is located on said block.

  • Held bi-weekly progress meeting to address old and new issues with the contractor and other project stakeholders.

 

Weekly Report: 11/23/12 (click to expand)

Click here to view this week's report in pdf format

Project Progress

  • No work performed on Thursday and Friday due to Thanksgiving holiday.

  • Contractor, CPDC, installed curb, gutter and brick pavers on the north side of the 900 block of U Street NW.

  • Subcontractor, M.C. Dean, laid conduit on the1100 and 1200 blocks of U Street NW on the south side.

Public Outreach/Coordination

  • Held 900 block field meeting on November 20th to inform occupants in the 900 block of upcoming activities that will take place. Those in attendance were given the opportunity to ask questions and voice concerns pertaining to construction activities in the 900 block and throughout the projects.

 

Weekly Report: 11/16/12 (click to expand)

Click here to view this week's report in pdf format

Project Progress

  • Contractor, CPDC, constructed bus pads in the 900, 1100 and 1200 blocks of U Street NW

  • Contractor, CPDC, saw cut the roadway on the 1100 and 1200 blocks of U Street NW on the south side.

  • Subcontractor, M.C. Dean, laid conduit on the1100 and 1200 blocks of U Street NW on the south side.

  • Contractor, CPDC, excavated for granite curb installation on the 900 block of Street NW on the north side.

  • DDOT materials division was on site performing density tests on the 900 block of U Street on the north side.

Public Outreach/Coordination

  • Distributed information to the public about the 900 block field meeting that will take place on November 20, 2012 to inform occupants in the 900 block of upcoming activities.

  • Spoke with 900 block occupant that cannot attend field meeting about scheduling. Occupant was made aware of current schedule and will be contacted in the future as we proceed.

 

Weekly Report: 11/09/12 (click to expand)

Click here to view this week's report in pdf format

Project Progress

  • Contractor did not work Thursday due to weather.

  • Subcontractor, M.C. Dean, laid conduit on the 1300 block of U Street NW on the north side; and on the 1000, 1100 and 1200 blocks of U Street NW on the south side.

  • Contractor, CPDC, saw cut the roadway on the 1000, 1100 and 1200 blocks of U Street NW on the south side.

  • Contractor constructed bus pads in the 900, 1000 and 1200 blocks of U Street NW.

Public Outreach/Coordination

  • Distributed information to the public about the 900 block field meeting that will take place on November 20, 2012 to inform occupants in the 900 block of upcoming activities.

  • Notified the public about temporary bus stop locations for the upcoming work week.

  • Spoke with Intowner editor about project progress. Article can be found online.

Weekly Report: 11/02/12 (click to expand)

Click here to view this week's report in pdf format

Project Progress

  • Contractor did not work Monday and Tuesday due to weather.

  • Subcontractor, M.C. Dean, laid conduit on the 1300 block of U Street NW on the north side; and on the 900 block of U Street NW on the south side.

  • Contractor, CPDC, saw cut the roadway on the 1000 blocks of U Street NW on the south side.

  • Contractor, CPDC, performed trench repair on the 900 and 1000 blocks on the north and south sides of U Street NW.

Public Outreach/Coordination

  • Attended ANC1B monthly meeting and addressed all questions and concerns from the public in regards to the construction activities on U Street NW.

  • Rahmat Rasson from DDOT streetlight and traffic signal department was on site with HNTB adjusting plans and solving several light and signal plan conflicts.

Weekly Report: 10/25/12 (click to expand)

Project Progress

Click here to view this week's report in pdf format

  • Subcontractor, M.C. Dean, laid conduit on the 1200 and 1300 blocks of U Street NW on the north side; and on the 900 and 1000 blocks of U Street NW on the south side.

  • Contractor, CPDC, saw cut the roadway on the 900 and 1000 blocks of U Street NW on the south side.

  • Contractor, CPDC, installed electrical manholes on the 1100 block and traffic signal manholes on the 1300 block.

Public Outreach/Coordination

  • Spoke with ANC1B commissioner and inquired about any concerns that have been brought up since the project restarted. None have been noted.

  • Worked with the contractor to be sure that construction equipment does not interfere with available parking space. Continued to monitor parking in the area to be sure that available spaces remained unobstructed.

  • Ian Owens from PEPCO was on site inquiring about CPDC crossing PEPCO transmission lines in the intersection of U Street NW and 13th Street NW. He will be back on site next week; weather permitting.

  • Volkert requested that DDOT streetlight and traffic signal representatives visit the site to review conflicts. After seeing that many conflicts existed, DDOT agreed that the streetlight and signal system designer should to come to the project site to review plans, and resolve streetlight and signal conflicts.

 

 

Weekly Report: 10/19/12 (click to expand)

Project Progress

Click here to view this week's report in pdf format

  • The required WMATA permit has been issued and Capital Paving DC (CPDC) has begun to excavate per WMATA instruction.

  • Subcontractor, M.C. Dean, laid conduit on the 1100 blocks of U Street NW on the north side.

  • Contractor, CPDC, installed electrical manholes on the 1100 block and traffic signal manholes on the 1300 block.

  • Contractor, CPDC, saw cut the roadway on the 1100 block.

Public Outreach/Coordination

  • Fielded calls/emails from the public inquiring about the project.

  • WMATA inspector was on site to ensure Metro grates were protected.

  • Spoke with business owner about concerns and scheduling.

Weekly Report: 10/12/12 (click to expand)

Project Progress

Click here to view this week's report in pdf format

  • The required WMATA permit has been issued and Capital Paving DC (CPDC) has begun to excavate per WMATA instruction.

  • Subcontractor, M.C. Dean, laid conduit on the 900 a nd 1000 blocks of U Street NW on the north side.

  • Contractor, CPDC, installed electrical manholes on the northeast corners of U Street NW at 13th Street.

Public Outreach/Coordination

  • Fielded calls/emails from the public inquiring about the project.

  • WMATA inspector was on site to ensure Metro grates were protected.

  • Spoke with business owner about concerns and scheduling.

Weekly Report: 10/05/12 (click to expand)

Project Progress

Click here to view this week's report in pdf format

  • The required WMATA permit has been issued and Capital Paving DC (CPDC) is now permitted to excavate per WMATA instruction.

  • Subcontractor, M.C. Dean, laid conduit on the 900 block of U Street NW on the north side.

  • Contractor, CPDC, installed electrical manholes on the northeast and northwest corners of U Street NW at 10th Street NW and the northeast corner of 11th Street.

Public Outreach/Coordination

  • Fielded calls/emails from the public about the project.

  • Attended monthly ANC1B meeting to update community about the project.

Weekly Report: 9/28/12 (click to expand)

Click here to view this week's report in pdf format

Project Progress

  • The required WMATA permit has been issued and Capital Paving DC (CPDC) is now permitted to excavate per WMATA instruction.

  • No work completed this week.

Public Outreach/Coordination

  • Fielded calls/emails from the public about the project.

  • Distributed press release to announce that construction activities will resume on October 1, 2012.

Weekly Report: 9/21/12 (click to expand)

Click here to view this week's report in pdf format

Project Progress

  • Capital Paving DC (CPDC) is still on hold and cannot excavate per WMATA instruction. The required permit is still under WMATA review.

  • No work completed this week.

Public Outreach/Coordination

  • Fielded calls/emails from the public about the project.

Weekly Report: 9/14/12 (click to expand)

Click here to view this week's report in pdf format

Project Progress

  • Capital Paving DC (CPDC) is still on hold and cannot excavate per WMATA instruction. The required permit is still under WMATA review.

  • No work completed this week.

Public Outreach/Coordination

  • Attended monthly ANC1B meeting to update public about project.

  • Fielded calls/emails from the public about the project.

Weekly Report: 9/07/12 (click to expand)

Click here to view this week's report in pdf format

Project Progress

  • Capital Paving DC (CPDC) is still on hold and cannot excavate per WMATA instruction. The required permit is still under WMATA review.

  • No work completed this week.

Public Outreach/Coordination

  • Attended monthly ANC1B meeting to update public about project.

  • Fielded calls/emails from the public about the project.

Weekly Report: 8/31/12 (click to expand)

Click here to view this week's report in pdf format

Project Progress

  • Capital Paving DC (CPDC) is still on hold and cannot excavate per WMATA instruction. The required permit is still under WMATA review.

  • No work completed this week.

Public Outreach/Coordination

  • Fielded calls/emails from the public about the project.

Weekly Report: 8/17/12 (click to expand)

Click here to view this week's report in pdf format

Project Progress

  • Capital Paving DC (CPDC) is still on hold and cannot excavate per WMATA instruction. The required permit is still under WMATA review.

  • Under a PEPCO contract and not part of this DDOT contract, B. Frank Joy was working in the 900 Block of U St. installing electrical service to 913 U St.Project Progress

Public Outreach/Coordination

  • Fielded calls/emails from the public about the project.

  • Transmitted CAD Files to Jack Story with Bowman Consulting (designer for the renovation of the Rite Aid Bldg. at the southwest corner of U & 13th Streets).

Weekly Report: 8/10/12 (click to expand)

Click here to view this week's report in pdf format

Project Progress

  • Capital Paving DC (CPDC) is still on hold and cannot excavate per WMATA instruction. The required permit is still under WMATA review.

  • Under a PEPCO contract and not part of this DDOT contract, B. Frank Joy was working in the 900 Block of U St. installing electrical service to 913 U St.Project Progress

Public Outreach/Coordination

  • Fielded calls/emails from the public about the project.

  • Transmitted CAD Files to Jack Story with Bowman Consulting (designer for the renovation of the Rite Aid Bldg. at the southwest corner of U & 13th Streets).

 

Weekly Report: 7/27/12 (click to expand)

Click here to view this week's report in pdf format

Project Progress

  • Sawcut concrete pavement for installation of electrical manholes and electrical duct in the 1200 block on the south side of U Street.

  • Volkert and DDOT met with Jerry Lyle of DDOT’s Parking Meter Division to discuss RFI #1: Pay-to-Park Signage; and the proposed signage per the contract drawings.

  • CPDC layout and marked stationing along the south side from 9th to 14th Streets.

  • Capital Paving DC (CPDC) is still on hold and cannot excavate per WMATA instruction. The required permit is still under WMATA review.

Public Outreach/Coordination

  • Fielded calls/emails from the public about the project.

Weekly Report: 7/20/12 (click to expand)

Click here to view this week's report in pdf format

Project Progress

  • Sawcut concrete pavement for installation of electrical manholes and electrical duct in the 1300 block on the south side of U Street.

  • Capital Paving DC (CPDC) is still on hold and cannot excavate per WMATA instruction. The required permit is still under WMATA review.

Public Outreach/Coordination

  • Fielded calls/emails from the public about the project.

  • Addressed scheduling with 1100 block business owner.

Weekly Report: 7/13/12 (click to expand)

Click here to view this week's report in pdf format

Project Progress

  • Sawcut concrete pavement for installation of electrical manholes and electrical duct from 13th Street to the west end of the project limits.

  • Capital Paving DC (CPDC) is still on hold and cannot excavate per WMATA instruction. The required permit is still under WMATA review.

Public Outreach/Coordination

  • Fielded calls/emails from the public about the project.

  • Addressed scheduling concerns with 900 block new-business owner

  • Met with stakeholders of Ben’s Chili Bowl to discuss plans and current conditions.

 

Weekly Report: 7/06/12 (click to expand)

Click here to view this week's report in pdf format

Project Progress

  • Sawcut and hoe-ram asphalt/concrete pavement for installation of electrical manholes and electrical duct from 11th Street to 13th Street.

  • Installed tree-protection fencing around existing trees at 11th Street to 13th Street on the north side.

  • Capital Paving DC (CPDC) is still on hold and cannot excavate per WMATA instruction. The required permit is still under WMATA review.

Public Outreach/Coordination

  • Fielded calls/emails from the public about the project.

  • Attended ANC1B monthly meeting to discuss project progress and address and questions and/or concerns from the community.

 

Weekly Report: 6/29/12 (click to expand)

Click here to view this week's report in pdf format

Project Progress

  • Sawcut and hoe-ram asphalt/concrete pavement for installation of electrical manholes and electrical duct from 10th Street to 12th Street.

  • Installed tree-protection fencing around existing trees at 11th Street to 13th Street on the north side.

  • Met with an individual of Xerox regarding the locations of proposed multi-space pay and display parking meters.

  • Notified by Capital Paving DC (CPDC) that because their WMATA permit is not fully executed, CPDC is not allowed to excavate within the project limits per WMATA.

Public Outreach/Coordination

  • Met with an individual to provide him with details about the project and to obtain information about the Dog Days event in August.

  • Met with DDOT staff regarding the project details to be included in an upcoming DDOT newsletter.

  • Met with a local business owner about his concerns with construction and answered his questions.

  • Fielded calls/emails from the public about the project.

 

 

 

 

 

weekly update

Click above to view the latest weekly report in PDF format.

 